In a significant step towards improving speed, safety, and operational efficiency, the Engineering Department of Eastern Railways Howrah Division has successfully executed a critical track realignment work between Cheragram Block Hut and Belmuri station on the Down Howrah - Barddhaman chord line. The work was carried out between 18th and 20th July 2025 and marks a major achievement in track maintenance and optimization.

A force layout was successfully removed through meticulous slewing operations using BCM (Ballast Cleaning Machine) and Tamping machine (MFI) during three separate traffic blocks in the mentioned period.

This work was meticulously planned and executed by Shri Partha De, SSE/P.Way/Gurap (SEC), under the guidance of Shri Vivek Thakur, PWI In-charge/Gurap, and with overall supervision and support from Shri Alok, AEN/Dankuni and Shri R.K. Barnwal, Sr. DEN- 2/Howrah.

The key achievements of the work include improvement of track geometry by correcting the false curve, which will reduce rail wear and enhance both safety and passenger ride comfort. Additionally, two reverse curves Curve No. 27 and Curve No. 28 were also successfully removed, resulting in improved alignment and operational efficiency.

This achievement significantly contributes to improved punctuality and reduced maintenance needs, thereby benefiting both passengers and freight operations. The Engineering Departments proactive approach and technical excellence continue to reinforce Eastern Railways commitment to enhancing infrastructure and ensuring passenger satisfaction.